1. What LCOE Is
The levelized cost of electricity is the constant price per megawatt-hour that, over the whole life of a plant, exactly recovers every cost at the assumed discount rate. It collapses a project with a large up-front capital spend and decades of variable fuel and maintenance cost into one comparable number.
Formally it is the ratio of discounted lifetime cost to discounted lifetime output:
In practice, when output and costs are roughly constant year to year, this reduces to the annualized form used by EIA, NREL and IEA/NEA, and by the calculator: annualize the capital, then divide everything by annual generation.
2. Capital Recovery Factor
Capital is spent once, but recovered over decades, and money has a time cost. The capital recovery factor converts a lump-sum capital cost into the equivalent constant annual payment — mathematically identical to a mortgage payment:
At 8% over 30 years, CRF = 0.0888. A plant costing $1,330/kW therefore carries $118.1/kW-yr of capital recovery. Note how strongly this depends on the discount rate:
| Discount rate | CRF (30 yr) | Annual capital on $1,330/kW |
|---|---|---|
| 5% | 0.0651 | $86.5/kW-yr |
| 7% | 0.0806 | $107.2/kW-yr |
| 8% | 0.0888 | $118.1/kW-yr |
| 10% | 0.1061 | $141.1/kW-yr |
| 12% | 0.1241 | $165.1/kW-yr |
3. The Full Build-Up
Every term is reduced to dollars per MWh of net generation. A 1 kW plant at capacity factor CF generates 8,760 × CF kWh per year, so annual per-kW costs are divided by that output:
Where the unit factors come from
These constants are not arbitrary — each is a unit conversion:
- 1000 / (8760 × CF) — one kW at capacity factor CF produces 8,760 × CF kWh/yr, or 8.76 × CF MWh/yr. Dividing $/kW-yr by that gives $/MWh.
- HR / 1000 — heat rate in Btu/kWh times 1,000 kWh/MWh, divided by 106 Btu/MMBtu, gives MMBtu per MWh.
- EF / 106 — converts kg CO₂/MMBtu through MMBtu/MWh to tonnes CO₂/MWh.
Thermal efficiency
Heat rate and efficiency are the same statement inverted. One kWh is exactly 3,412.14 Btu, so:
4. Why Capacity Factor Dominates
Capital recovery and fixed O&M are fixed dollars per year. They do not care how much the plant runs. Divide them by a small number of MWh and the per-unit cost explodes. This single effect explains most of the spread between published LCOE figures.
Taking the same $1,330/kW combined-cycle reference plant at 8% and 30 years, varying only capacity factor:
| Capacity factor | Capital + fixed O&M | Fuel + variable | LCOE |
|---|---|---|---|
| 10% | $153.0/MWh | $25.4/MWh | $178.4/MWh |
| 20% | $76.5/MWh | $25.4/MWh | $101.9/MWh |
| 40% | $38.2/MWh | $25.4/MWh | $63.6/MWh |
| 60% | $25.5/MWh | $25.4/MWh | $50.9/MWh |
| 85% | $18.0/MWh | $25.4/MWh | $43.4/MWh |
The fuel term is flat because it is charged per MWh produced. Everything else is leverage on utilization.
5. From MW to MMscf/d
Power projects are announced in megawatts. The midstream consequence is volume, and the conversion runs through heat rate:
Worked through for a 418 MW combined cycle at 6,431 Btu/kWh and 60% capacity factor:
As a planning rule of thumb, a combined-cycle plant at full load consumes roughly 14–16 MMscf/d per 100 MW (15.0 at 6,431 Btu/kWh). The annual-average rate is lower by the capacity factor — about 9 MMscf/d per 100 MW at 60% — so the two must never be interchanged. A less efficient simple-cycle unit consumes proportionally more per MWh but usually runs far fewer hours.
Large new electrical loads are specified in MW, but delivering them requires gas supply, processing and pipeline capacity in MMscf/d. This conversion is the bridge between a generation project and the midstream system that feeds it.
6. Worked Example
A combined-cycle plant serving a steady industrial load, using the EIA AEO 2023 single-shaft reference plant.
Step 1: Capital recovery factor
Step 2: Annualize capital and spread over output
Step 3: Fuel and variable
Step 4: Total
7. What LCOE Does Not Tell You
LCOE is deliberately narrow. Used outside its scope it misleads:
- It ignores when the power is produced. A MWh at 5 pm on a summer peak is worth far more than one at 3 am. LCOE treats them identically.
- It ignores capacity value. Dispatchable plants provide firm capacity and reserves that intermittent resources cannot, and that value appears nowhere in $/MWh.
- It excludes system costs. Transmission, interconnection, backup and curtailment are outside the plant boundary.
- It is highly sensitive to assumptions. Discount rate, capacity factor and fuel price each move the answer by tens of percent, so comparisons are only valid on a common basis.
- It assumes level output and costs. Real degradation, major overhauls and escalating O&M require a full discounted cash-flow model.
References
- U.S. EIA — Cost and Performance Characteristics of New Generating Technologies, Annual Energy Outlook 2023 (March 2023), Table 1. Source of every plant-type preset: total overnight cost (2022$/kW), fixed and variable O&M, and HHV heat rate.
- NREL — Annual Technology Baseline: The 2024 Electricity Update. The ATB's fossil cost and performance derive from NETL/FECM sources rather than EIA; only the rate of cost improvement is taken from AEO2023. ATB also applies a fixed charge rate (FCR = CRF × financial factors) rather than a plain CRF, which raises the capital term by roughly 9%.
- IEA / NEA — Projected Costs of Generating Electricity, levelized cost methodology.
- EPA 40 CFR 98 Subpart C, Table C-1 — Default CO2 Emission Factors and High Heat Values. Natural gas (weighted U.S. average): 53.06 kg CO2/mmBtu and 1.026×10−3 mmBtu/scf (1,026 Btu/scf). Source of both the emission factor and the gas heating value used here.
- EPA AP-42, Table 3.1-2a — Stationary Gas Turbines, CO2 110 lb/MMBtu (49.90 kg/MMBtu), Rating A, based on 99.5% carbon conversion. A turbine-specific combustion factor about 6% below the 40 CFR 98 reporting value; it does not cover reciprocating engines (AP-42 Ch. 3.2).
On default values: the plant-type presets are taken directly from EIA AEO 2023 Table 1 (2022 dollars) and represent generic new-build plants, not any specific project. Capacity factor is not an EIA technology characteristic — it is a dispatch outcome — so those defaults are typical operating duty only. LCOE is dominated by project-specific capital cost, financing and delivered fuel price: always replace the presets with project data before drawing conclusions.