Capital Cost Estimate (AACE 18R-97)

Economics ยท Cost class & accuracy range ยท AACE 18R-97

AACE Cost Estimate Classification
Applies location, escalation and contingency to a base estimate and returns the Total Installed Cost with the AACE 18R-97 accuracy bands for the selected class.

Estimate

USD

Adjustments

%
%

Engineering Basis

  • TIC = base ร— location ร— (1+escalation) ร— (1+contingency).
  • Accuracy bands (process industries): Class 5 โˆ’50/+100%, 4 โˆ’30/+50%, 3 โˆ’20/+30%, 2 โˆ’15/+20%, 1 โˆ’10/+15%.
  • Class set by project-definition maturity; TIC โ‰ˆ P50, low โ‰ˆ P10, high โ‰ˆ P90.
  • Standards: AACE International 18R-97.