Gas Processing

NGL Recovery & Process Efficiency

Maximize NGL recovery while minimizing energy consumption through proper process selection, heat integration, and equipment optimization per GPSA Section 16.

Ethane recovery (turboexpander)

90-95%

Best-in-class cryogenic plants at -100°F, 300-450 psig.

Propane recovery

98-99%

Refrigerated lean oil or JT plants at -40°F.

Energy savings potential

20-40%

Via heat integration, pinch analysis, and expander optimization.

Use this guide when:

  • Evaluating NGL recovery process options
  • Optimizing existing plant efficiency
  • Analyzing energy consumption vs. product value

1. NGL Recovery Processes

NGL recovery extracts ethane, propane, butanes, and heavier hydrocarbons from natural gas. The process selection depends on feed composition, product specifications, and economics. Recovery efficiency is primarily controlled by temperature - lower temperatures yield higher recovery but require more energy.

Turboexpander (GSP)

90-95% C2 Recovery

Cryogenic process at -100°F. Gas Subcooled Process (GSP) is industry standard for high ethane recovery.

JT (Joule-Thomson)

40-70% C2 Recovery

Simple isenthalpic expansion. Lower capital, suitable for lean gas or ethane rejection.

Refrigerated Lean Oil

70-85% C2 Recovery

Absorption process using chilled lean oil. Good for moderate NGL content.

Nitrogen Rejection (NRU)

90-97% N₂ Rejection

Double-column cryogenic at -260°F. Required when feed N₂ exceeds pipeline spec.

Process flow diagram of turboexpander NGL recovery plant showing inlet separator V-100, gas-gas exchanger E-101 with temperature annotations (100°F feed, -60°F post-exchanger, -100°F post-expander), turboexpander T-100, demethanizer column T-101, and residue compressor C-100 with work recovery shaft connection
Turboexpander plant PFD showing key equipment and temperature profile for cryogenic NGL recovery per GPSA Section 16.

Ethane Recovery vs. Temperature

Recovery efficiency follows thermodynamic equilibrium. The relationship between process temperature and recovery is nonlinear - significant improvements require increasingly lower temperatures.

Ethane Recovery Correlation (GPSA Section 16): At 450 psig operating pressure: Temperature (°F) C2 Recovery (%) -100 98.0 -80 95.0 -60 86.0 -40 68.0 -20 43.0 0 20.0 Key relationships: • Each 20°F temperature reduction → 10-15% recovery increase • Higher pressure = lower recovery at same temperature • C3+ recovery is always higher than C2 at same conditions Economics example: Feed: 100 MMscfd, 10% C2 (10 MMscfd ethane) At -40°F: 68% recovery → 6.8 MMscfd C2 recovered At -100°F: 98% recovery → 9.8 MMscfd C2 recovered Additional recovery: 3.0 MMscfd At $0.25/gal ethane (2.37 gal/Mscf): Additional revenue = 3,000 Mscfd × 2.37 gal/Mscf × $0.25/gal = $1,778/day = $649K/year Energy cost for -60°F additional cooling: ~0.5 MMBtu/MMscf × 100 MMscfd × $3/MMBtu = $150/day = $55K/year Net benefit: ~$594K/year (justifies turboexpander investment)

Process Selection Guide

Process C2 Recovery C3+ Recovery Typical Temperature Best Application
GSP (Gas Subcooled Process) 90-95% 99+% -100 to -120°F Rich gas, high ethane value
SCORE (Single Column ORE) 92-97% 99+% -100 to -130°F Maximum C2 recovery
CRR (Cold Residue Recycle) 85-92% 99+% -90 to -110°F High CO₂ feeds
JT + External Refrigeration 50-75% 95-98% -40 to -60°F Moderate NGL, low capital
Straight JT 20-50% 80-95% -20 to -40°F Lean gas, C2 rejection
Refrigerated Lean Oil 70-85% 95-99% -30 to -50°F Older plants, retrofits
Ethane rejection mode: When ethane prices are low relative to natural gas, plants operate in "ethane rejection" mode by increasing temperature to ~0°F. This reduces C2 recovery to 20-30%, leaving ethane in the sales gas (increasing its heating value) while still recovering 90%+ C3+. The ability to swing between ethane recovery and rejection provides operational flexibility to optimize economics based on market conditions.

2. Efficiency Metrics

Process efficiency measures how effectively inputs are converted to outputs. For NGL plants, key metrics include component recovery, energy consumption per unit product, and comparison to thermodynamic limits.

Key Efficiency Definitions

Recovery Efficiency: η_recovery = (Component recovered in NGL) / (Component in feed) × 100% Example - Ethane Recovery: Feed: 100 MMscfd at 10 mol% C2 = 10 MMscfd C2 NGL product: Contains 9.2 MMscfd C2 η_C2 = 9.2 / 10.0 × 100% = 92% Specific Energy Consumption: SEC = Total energy input / Product output Units: MMBtu/MMscf NGL, kWh/gal NGL, BTU/lb NGL Typical values (turboexpander plants): • Rich gas (6+ GPM): 0.6-0.8 MMBtu/MMscf NGL • Lean gas (2-4 GPM): 1.0-1.5 MMBtu/MMscf NGL GPM (Gallons per Mscf): Standard measure of NGL content in feed gas. GPM = Σ (Component mol% × GPM factor) GPM factors at 60°F, 14.7 psia: C2 = 2.37 gal/Mscf per mol% C3 = 3.14 gal/Mscf per mol% iC4 = 3.56 gal/Mscf per mol% nC4 = 3.59 gal/Mscf per mol% C5+ = 4.0-5.0 gal/Mscf per mol% Example: Feed composition: 8% C2, 4% C3, 2% C4+ GPM = 8×0.0237 + 4×0.0314 + 2×0.036 = 0.19 + 0.13 + 0.07 = 0.39 × 100 = 3.9 GPM Shrinkage: Reduction in sales gas volume due to NGL extraction. Shrinkage% = (Feed volume - Residue volume) / Feed volume × 100% Typical: 5-15% for rich gas plants

Energy Balance for NGL Plant

Understanding where energy is consumed enables optimization:

Energy Consumer % of Total Typical Load Optimization Opportunity
Residue gas compression 35-50% 5,000-20,000 HP Maximize expander work recovery
Refrigeration compressor 20-35% 2,000-10,000 HP Heat integration, optimal staging
Demethanizer reboiler 10-20% 5-20 MMBtu/hr Optimize reflux ratio, feed preheat
Inlet compression (if any) 0-15% 0-5,000 HP Optimize inlet pressure
Utilities (pumps, air coolers) 5-10% 500-2,000 HP VFDs, efficient motors
Sankey diagram showing NGL recovery plant energy flows: 25 MMBtu/hr fuel gas input branching to residue compression 12 MMBtu/hr (48%), refrigeration 6 MMBtu/hr (24%), demethanizer reboiler 4 MMBtu/hr (16%), utilities 2 MMBtu/hr (8%), losses 1 MMBtu/hr (4%), with 8 MMBtu/hr expander work recovery offsetting compression
Energy flow distribution in NGL plant showing compression as dominant consumer (48%) and expander work recovery reducing net energy to 17 MMBtu/hr.
Turboexpander energy recovery: The turboexpander is key to efficient cryogenic plants. It performs isentropic expansion (unlike JT valve which is isenthalpic), producing work that drives the residue compressor. A well-designed expander recovers 60-80% of residue compression power, dramatically reducing net energy consumption. Expander efficiency of 85-88% is typical; below 80% indicates fouling or mechanical issues.

3. Heat Integration & Pinch Analysis

Heat integration maximizes heat recovery between process streams, minimizing external heating and cooling utilities. Pinch analysis provides a systematic methodology to identify the optimal heat exchanger network.

Pinch Analysis Fundamentals

Pinch Analysis Steps: 1. Extract stream data: For each stream: T_supply, T_target, ṁ×Cp (heat capacity rate) Classify as Hot (needs cooling) or Cold (needs heating) 2. Construct composite curves: Hot composite: cumulative enthalpy vs temperature for all hot streams Cold composite: same for cold streams 3. Set minimum approach (ΔT_min): Typical: 10-20°F for cryogenic, 20-40°F for ambient exchangers Trade-off: smaller ΔT_min = more recovery but larger exchangers 4. Identify pinch point: Location where composites are closest (separated by ΔT_min) Divides problem into two regions: • Above pinch: heat sink (requires hot utility) • Below pinch: heat source (requires cold utility) 5. Design network following "golden rules": • Never transfer heat across pinch • No cold utility above pinch • No hot utility below pinch NGL Plant Heat Integration Example: Hot streams (need cooling): H1: Inlet gas, 100°F → -100°F, CP = 50,000 BTU/hr·°F H2: Residue gas from column, -140°F → 100°F, CP = 45,000 BTU/hr·°F Cold streams (need heating): C1: Demethanizer feed, -100°F → -50°F, CP = 30,000 BTU/hr·°F C2: NGL product, -140°F → 60°F, CP = 10,000 BTU/hr·°F Without integration: External cooling = 50,000×200 + 45,000×240 = 20.8 MMBtu/hr External heating = 30,000×50 + 10,000×200 = 3.5 MMBtu/hr With pinch analysis (ΔT_min = 10°F): Pinch at -90°F Maximum heat recovery = 18 MMBtu/hr Minimum external cooling = 2.8 MMBtu/hr (87% reduction) Minimum external heating = 0.5 MMBtu/hr (86% reduction)
Temperature-Enthalpy diagram for pinch analysis showing hot composite curve (red) and cold composite curve (blue) with green shaded heat recovery zone, pinch point at ΔTmin=10°F, QH,min=0.5 MMBtu/hr hot utility, QC,min=2.8 MMBtu/hr cold utility, and maximum heat recovery of 18 MMBtu/hr
Composite curves for pinch analysis identifying minimum utility requirements (QH,min, QC,min) and maximum heat recovery potential.

Gas-Gas Exchanger Design

The gas-gas exchanger is the heart of cryogenic NGL plants, recovering cold from residue gas to precool inlet gas:

Parameter Typical Value Impact of Poor Design
Cold-end approach (LMTD) 5-15°F Larger approach = more refrigeration required
Effectiveness (ε) 90-95% Lower ε = higher energy consumption
Pressure drop (per side) 2-5 psi Higher ΔP = more compression power
UA (overall conductance) 10-50 MMBtu/hr·°F Fouling reduces UA, increases utilities
Brazed aluminum heat exchangers (BAHX): Cryogenic NGL plants use BAHX for gas-gas exchangers due to their high surface area per volume (up to 1,500 ft²/ft³), close temperature approach capability (5°F), and ability to handle multiple streams in a single core. BAHX require clean, dry gas - CO₂ and water must be removed upstream to prevent freezing and exchanger damage. Typical BAHX service life exceeds 30 years with proper operation.

4. Equipment Efficiency

Individual equipment efficiency directly impacts overall plant performance. Degradation from fouling, wear, or off-design operation can increase energy consumption 10-30%.

Turboexpander Efficiency

Turboexpander Performance: Isentropic efficiency: η_exp = (h_in - h_out,actual) / (h_in - h_out,isentropic) Typical: 85-88% (new), 80-85% (after 5 years) Temperature drop: ΔT_actual = η_exp × ΔT_isentropic Power recovered: HP = ṁ × (h_in - h_out) / 2545 Example: Feed: 100 MMscfd, MW = 20, inlet 500 psia / 60°F Outlet: 250 psia η_exp = 85% Isentropic ΔT = 60°F × [1 - (250/500)^0.23] = 60 × 0.15 = 9°F... [More complex calculation for real gas - actual ΔT ≈ 80-100°F] Power = ~3,000 HP recovered (drives residue compressor booster) Efficiency Degradation Causes: • Liquid carryover: Erodes blades, -2-5% efficiency • Fouling: Hydrocarbon deposits on wheel, -1-3% • Seal leakage: Bypass around wheel, -1-5% • Off-design speed: Operating far from best efficiency point Monitoring: Track ΔT across expander vs design curve Efficiency drop > 5% → schedule inspection

Compressor Efficiency

Residue Compressor Performance: Isentropic efficiency: η_comp = (T_out,isen - T_in) / (T_out,actual - T_in) Typical centrifugal: 75-82% Typical reciprocating: 80-88% Power requirement: HP = (ṁ × Cp × T_in / η_comp) × [(P_out/P_in)^((k-1)/k) - 1] × (k/(k-1)) Simplified: HP ≈ Q_acfm × ΔP_psi / (229 × η_comp) Energy cost of inefficiency: 5000 HP compressor, η drops from 80% to 75%: Power increase = 5000 × (0.80/0.75 - 1) = 333 HP Fuel penalty = 333 HP × 8000 hr/yr × 9500 BTU/HP·hr / 0.30 turbine eff = 84 MMscf/yr fuel increase Cost @ $3/MMBtu = $252K/year Cleaning cost: $50K → Payback: 2.4 months

Demethanizer Column Efficiency

The demethanizer separates methane from NGL. Efficient operation requires proper reflux ratio and tray hydraulics:

Parameter Target Symptom of Problem
C1 in NGL bottoms < 1.5 mol% High = insufficient reflux or trays
C2 in overhead < 2% of feed C2 High = too much reflux (energy waste) or temperature too high
Tray efficiency 65-75% Low = fouling, damage, maldistribution
Reflux ratio 1.2-1.5 × minimum High = excess reboiler duty
Column ΔP Per design ± 10% High = flooding or fouling
Advanced process control (APC): Implementing APC on the demethanizer typically saves 5-10% reboiler duty while maintaining or improving product specs. APC optimizes reflux ratio in real-time based on feed composition changes, minimizing energy while respecting constraints. Typical APC project cost: $200-500K. Payback: 6-18 months for 100+ MMscfd plants.

5. Performance KPIs

Systematic KPI monitoring identifies efficiency degradation early, enabling corrective action before significant losses occur. Track both energy and production metrics.

Key Performance Indicators

KPI Calculation Target Action Threshold
C2 recovery efficiency C2 in NGL / C2 in feed × 100% Design ± 2% < Design - 5% → investigate
C3+ recovery C3+ in NGL / C3+ in feed × 100% > 98% < 95% → check temperature, trays
Specific energy Total energy / NGL produced Benchmark ± 10% > Benchmark + 15% → energy audit
Expander efficiency From T, P measurements > 82% < 80% → inspect, clean
Compressor efficiency Isentropic / actual work > 76% < 74% → cleaning, inspection
Heat exchanger UA Q / LMTD Design ± 15% < Design - 20% → clean
Plant availability Operating hrs / total hrs > 95% < 92% → reliability review

Benchmarking Data

Industry Benchmarks (GPSA, Solomon): NGL Recovery Plants (turboexpander): Best Average Poor C2 Recovery (%) 95+ 90-94 <88 C3+ Recovery (%) 99+ 97-98 <96 Specific Energy 0.6 0.8-1.0 >1.2 (MMBtu/MMscf NGL) Plant Availability (%) 98+ 94-96 <92 Energy Distribution: • Compression: 50-60% of total • Refrigeration: 20-30% • Heating (reboilers): 10-20% • Utilities: 5-10% Optimization Priorities: 1. Maximize expander work recovery (biggest impact) 2. Optimize cold-side heat integration 3. Minimize demethanizer reflux ratio 4. Reduce pressure drops throughout 5. Maintain equipment efficiency (cleaning, maintenance)
NGL plant performance dashboard with 4 panels: C2 Recovery Trend line chart showing 92.3% with 90-95% target band over 7 days, Specific Energy bar chart at 0.85 MMBtu/MMscf (+13% above 0.75 benchmark), Expander Efficiency gauge at 84% in green zone (82-90%), and Plant Availability calendar heatmap showing 96.2% MTD
Real-time KPI dashboard for NGL plant monitoring enabling rapid detection of efficiency degradation.
Continuous improvement cycle: Best-in-class operators follow a systematic improvement process: (1) Establish baseline performance during commissioning or after major turnaround, (2) Monitor KPIs weekly with automated alerts, (3) Investigate deviations within 48 hours, (4) Implement corrective actions and track results, (5) Re-baseline annually and set stretch targets (2-3% improvement/year). Typical result: 15-25% energy reduction over 5 years compared to status quo operation.