Facility Design

Equipment Spacing & Layout

Determine minimum equipment spacing distances for midstream facilities including compressor stations, gas processing plants, and production facilities. Apply requirements from API 2510, NFPA 30, and company-specific spacing guidelines for fire exposure protection and safe operations.

LPG storage

API 2510

Design and construction of LPG installations at production facilities. Covers spacing from LPG storage to other equipment.

Flammable liquids

NFPA 30

Flammable and combustible liquids code. Spacing requirements for tanks, process equipment, and buildings.

Gas plants

NFPA 59A / API 2510

Standard for gas plant spacing varies by company. Many operators follow API 2510 or internal standards.

Use this guide when you need to:

  • Determine minimum spacing between equipment items
  • Develop a facility plot plan for a new installation
  • Verify code compliance for equipment placement
  • Evaluate fire exposure distances
  • Plan compressor station and gas plant layouts

1. Equipment Spacing Overview

Equipment spacing in midstream facilities serves three critical safety functions: preventing fire escalation between equipment items, providing access for maintenance and emergency response, and maintaining safe distances from ignition sources. Proper spacing is one of the most fundamental safety measures in facility design.

Fire exposure

Prevent escalation

Adequate distance prevents a fire at one piece of equipment from igniting or damaging adjacent equipment. Radiation intensity decreases with the square of distance.

Access

Maintenance & emergency

Space for crane access, equipment removal, fire truck access roads, and personnel evacuation routes.

Operations

Day-to-day function

Space for operator rounds, instrument access, valve operation, chemical injection, and routine maintenance.

Spacing Measurement Points

Distances are measured from the nearest point of each equipment item, not from centerlines:

  • Vessels: From vessel shell (not nozzles or piping)
  • Tanks: From tank shell
  • Compressors: From compressor skid edge or package edge
  • Fired heaters: From the firebox or burner opening
  • Buildings: From building wall (nearest point)
  • Property lines: From nearest property boundary
  • Flares: From flare tip (radiant heat calculation governs)
Governing principle: Spacing distances in codes and standards represent minimums. Good engineering practice often requires larger spacing for maintenance access, future expansion, or specific hazard considerations. Always evaluate the specific hazards at your facility in addition to applying code minimum distances.

2. Applicable Codes & Standards

Standard Title Scope
API 2510Design and Construction of LPG InstallationsLPG storage spacing at production facilities
NFPA 30Flammable and Combustible Liquids CodeLiquid storage tank and process equipment spacing
NFPA 59AStandard for LNG Production, Storage, and HandlingLNG facility spacing
API 2510AFire Protection for LPGFire protection requirements complementing API 2510
49 CFR 192Transportation of Natural Gas by PipelineCompressor station spacing from buildings and boundaries
49 CFR 195Transportation of Hazardous Liquids by PipelineLiquid pipeline facility spacing
OSHA 1910.106Flammable LiquidsGeneral industry flammable liquid handling
NFPA 58Liquefied Petroleum Gas CodeLPG storage at non-production facilities

Hierarchy of Requirements

  • Federal regulations (49 CFR): Mandatory; apply to interstate pipeline facilities
  • State regulations: May be more restrictive than federal; always check
  • NFPA codes: Adopted by reference in most state and local fire codes
  • API standards: Industry recommended practices; often adopted by company policy
  • Company standards: Internal spacing policies often exceed code minimums
  • Insurance requirements: FM Global, Industrial Risk Insurers may require additional spacing
Compliance note: Multiple codes may apply to a single facility. The most restrictive requirement governs. Document which code applies to each spacing distance on the plot plan for future reference and regulatory audits.

3. Spacing Tables

General Equipment Spacing (Typical Industry Practice)

From To Min. Distance (ft) Basis
Process vesselProcess vessel10–15Maintenance access, fire exposure
Process vesselFired heater50–100Ignition source separation
Process vesselControl building50–100Personnel safety
CompressorProcess vessel25–50Vibration, fire exposure
CompressorFired heater50–100Ignition source separation
CompressorProperty line100–200Noise, fire radiation
Atmospheric tankProcess equipment50NFPA 30
Atmospheric tankProperty lineVaries by capacityNFPA 30, Table 22.4.2.1
Pressure vesselProperty line50–100Company/local code
Flare stackAny equipmentPer radiation calc.API 521 radiation limit

Distances are typical industry practice and vary by company, jurisdiction, and hazard analysis. Always verify against applicable codes and company standards for your specific facility.

LPG Storage Spacing (API 2510)

From LPG Storage To Min. Distance (ft)
LPG tank (< 30,000 gal)Property line / public way50
LPG tank (30,000–70,000 gal)Property line / public way75
LPG tank (> 70,000 gal)Property line / public way100
LPG tankControl building50
LPG tankFired equipment50
LPG tankOther LPG tank5 ft or 1/4 sum of diameters
LPG loading rackProperty line25

Tank Spacing (NFPA 30)

Tank Type To Adjacent Tank To Property Line
Floating roof (< 150 ft dia.)1/6 sum of diameters1/2 diameter (min 5 ft)
Fixed roof (< 150 ft dia.)1/6 sum of diameters1/2 diameter (min 5 ft)
Fixed roof (crude, > 150 ft dia.)1/4 sum of diametersVaries
Pressure vessel (horizontal)5 ft or 1/4 sum of diameters50 ft
Spacing tables are minimums: These tables provide code minimum distances. Good practice adds spacing for crane swing radius, pipe rack clearance, future expansion pads, and specific maintenance access requirements identified during HAZOP or constructability reviews.

4. Compressor Station Layout

Compressor stations have unique spacing requirements due to the presence of high-pressure gas, rotating equipment, noise, and vibration. Layout must accommodate both safety distances and operational access.

Compressor Station Spacing (49 CFR 192)

From To Requirement
Compressor buildingNearest building (off-site)Per DOT Class location (Table 192.111)
Compressor buildingProperty lineMinimum 200 ft recommended
Gas pipingBuildings not part of stationPer Class location requirements
Compressor unitCompressor unit10–20 ft (maintenance access)
Compressor buildingControl building50 ft minimum

Typical Compressor Station Layout Zones

  • Compressor zone: Compressor packages, suction and discharge scrubbers, coolers. Central location for piping efficiency.
  • Piping and valve zone: Suction and discharge headers, mainline valves, bypass piping. Adjacent to compressors.
  • Utilities zone: Fuel gas system, instrument air, lube oil storage, electrical switchgear. Separated from process by distance or fire wall.
  • Control zone: Control building, MCC building, telecommunications. Located upwind and at maximum practical distance from process.
  • Flare zone: Flare stack or enclosed ground flare. Located downwind per radiation calculations.
  • Access zone: Truck access roads (minimum 20 ft wide), crane pad areas, laydown areas for maintenance.

Access Road Requirements

Road Type Minimum Width (ft) Purpose
Main access road20–24Two-way traffic, emergency vehicle access
Perimeter road16–20Emergency access around facility
Equipment access aisle10–15Maintenance vehicle and forklift access
Pedestrian walkway4–6Operator access routes
Layout tip: Orient the compressor station with the control building upwind (prevailing wind direction) of the process area. Position the flare downwind. Ensure that at least two emergency exit routes exist from any point in the facility.

5. Fire Protection Considerations

Thermal Radiation Limits

Equipment spacing for fire exposure is based on limiting thermal radiation intensity at adjacent equipment and personnel locations:

Radiation Level (BTU/hr·ft²) Effect Application
500Equipment failure after prolonged exposureMinimum distance for unprotected steel vessels
1,500Piloted ignition of woodMinimum distance to combustible structures
2,000Pain threshold (prolonged exposure)Maximum at fenceline / property line
3,000Blistering in 20 secondsMaximum at areas of limited occupancy
5,000Structural steel weakeningMaximum at any normally occupied area

Fire Wall and Barrier Requirements

When minimum spacing cannot be achieved due to plot constraints, fire-rated barriers may be used as alternatives:

  • Fire walls: 2-hour fire-rated walls between equipment items. Must extend 2 ft beyond the protected equipment on each side.
  • Blast walls: Reinforced concrete or steel blast walls for explosion resistance. Typically 12–18 inches thick concrete.
  • Fire-proofing: Cementitious or intumescent fireproofing on structural steel, vessel skirts, and pipe supports within fire exposure zones.
  • Deluge systems: Water spray systems can substitute for some spacing requirements. Provides cooling during fire exposure.

Impoundment and Drainage

  • All liquid-containing equipment must have adequate drainage to prevent burning liquid from flowing to adjacent equipment
  • Impoundment areas (dikes, curbs) around tanks and vessels contain spills
  • Drainage should direct away from equipment, roads, and property lines
  • Impoundment volume: minimum 100% of largest tank + rainfall allowance
Fire protection hierarchy: The preferred approach to fire safety is (1) adequate spacing first, then (2) fire-rated barriers if spacing is insufficient, then (3) active fire protection systems (deluge, foam) as supplementary measures. Active systems require maintenance and can fail; passive measures (distance and barriers) are inherently more reliable.

6. Plot Plan Development

Plot Plan Development Process

  • Step 1: Develop equipment list with sizes, weights, and utility requirements
  • Step 2: Identify applicable spacing codes and company standards
  • Step 3: Create spacing matrix (equipment-to-equipment minimum distances)
  • Step 4: Determine prevailing wind direction, topography, and drainage
  • Step 5: Place equipment starting with the largest items and highest-hazard items
  • Step 6: Route access roads and establish emergency exit paths
  • Step 7: Verify all spacing requirements are met with a compliance check
  • Step 8: Review with operations, maintenance, and safety personnel

Equipment Placement Priority

Priority Equipment Rationale
1Control building / MCCPersonnel safety; upwind location; access for operations
2Flare / thermal oxidizerFixed by radiation calculation; downwind
3CompressorsCentral for piping; vibration isolation; noise
4Separators / scrubbersAdjacent to compressors for piping efficiency
5Storage tanksImpoundment area; fire spacing from process
6Coolers (ACHEs)Adequate air circulation; avoid recirculation
7Fired equipmentSeparated from hydrocarbon sources
8UtilitiesNear point of use; away from process hazards
Future expansion: Always allocate plot space for future expansion when designing a new facility. Reserve space for additional compressor units, treating equipment, or pipeline connections. It is far less expensive to reserve space during initial design than to retrofit spacing later.

7. Best Practices

Layout Review Checklist

  • All code-minimum spacing requirements verified and documented
  • Spacing matrix completed and attached to plot plan
  • Two emergency exit routes available from every point in the facility
  • Crane access paths clear for equipment removal (all major items)
  • Prevailing wind direction considered for control building and flare placement
  • Drainage slopes away from equipment and buildings
  • Fire truck access road continuous around the facility perimeter
  • Air cooler recirculation prevented (adequate clearance between units and from buildings)
  • Noise levels verified at property line and nearest receptor
  • Future expansion areas identified and reserved

Common Layout Mistakes

Mistake Consequence Prevention
Insufficient crane accessCannot remove equipment without disassemblyPlan crane swing radius for all major equipment
Blocked emergency exitsPersonnel trapped during emergencyModel evacuation routes; verify with walk-through
Ignition source too close to HC releaseImmediate ignition of releaseFollow spacing tables; locate fired equipment upwind
No expansion spaceCostly retrofit or new facility neededReserve 30–50% additional plot area
Drainage toward equipmentBurning liquid flows under equipmentGrade away from all equipment
Air cooler recirculationReduced cooling capacity in summerMinimum 1.5x fan diameter clearance between ACHEs

Constructability Considerations

  • Module delivery: If equipment is delivered as pre-assembled modules (skids), verify that access roads and gates accommodate module dimensions and weights.
  • Soil conditions: Foundation design affects spacing. Poor soils may require larger foundations that reduce available clearance between equipment.
  • Underground utilities: Map all underground piping, electrical conduit, and cable trays before finalizing the plot plan. Underground conflicts are expensive to resolve after construction begins.
  • Above-ground piping: Pipe rack routing affects equipment spacing. Plan pipe rack locations early in the layout process.
Review process: Conduct a formal layout review (also called a plot plan review or constructability review) with participation from process engineering, mechanical engineering, operations, maintenance, safety, and construction. This multi-discipline review catches spacing and access issues that single-discipline reviews miss.