Pipeline Design

Pipeline Crossing Design

Design and analyze pipeline crossings for roads, railroads, rivers, and foreign utilities per API 1102 and DOT 49 CFR 192 using Marston load theory and structural analysis.

API 1102

Steel Pipelines

Crossing highways and railroads

DOT 49 CFR 192

Minimum Cover

Class location depth requirements

Cased Crossing

Carrier + Casing

Double-pipe protection at crossings

Use this guide when:

  • Designing road or railroad pipeline crossings
  • Evaluating cased vs uncased crossing options
  • Calculating earth and live loads on buried pipe
  • Determining minimum cover depth per DOT 192

1. Overview

Pipeline crossings occur wherever a pipeline must pass beneath a road, railroad, river, canal, or foreign utility. These crossings require special engineering analysis because the pipeline is subjected to concentrated external loads from traffic, rail equipment, or hydrostatic forces in addition to the normal earth loads experienced along the rest of the route.

Road Crossings

Highway & County Roads

AASHTO HL-93 and H-20 live loads from vehicular traffic applied through pavement and soil.

Railroad Crossings

Cooper E-80 Loading

Heavy axle loads from locomotives and rolling stock, typically Cooper E-80 or E-72 rating.

River & Canal Crossings

HDD or Open Cut

Horizontal directional drilling or weighted pipe in open trench with scour protection.

Foreign Utility Crossings

Separation Requirements

Minimum clearance between pipelines and other buried utilities per local and federal codes.

Why crossings matter: Pipeline crossings concentrate external loads onto a short pipe segment. A properly designed crossing prevents overstress, excessive deflection, and third-party damage. API 1102 provides the industry-standard methodology for steel pipeline crossings at roads and railroads.

2. Crossing Types & Methods

The crossing installation method depends on the crossing width, traffic conditions, soil type, environmental sensitivity, and regulatory requirements.

Open-Cut Method

The pipeline trench is excavated across the road or railroad, the pipe is installed, and the surface is restored. This is the simplest and least expensive method but requires traffic interruption and surface restoration.

Open-Cut Advantages: - Lowest installation cost - Direct control of bedding and backfill - Visual inspection of pipe and coating - Simple alignment control Limitations: - Traffic disruption (road closure or detour required) - Surface restoration costs (pavement, rail, drainage) - Permitting delays for major highways and railroads - Environmental disturbance at waterways

Bore and Jack Method

A steel casing pipe is jacked or augered beneath the crossing from a launch pit to a receiving pit. The carrier pipe is then inserted into the casing with insulating spacers. This trenchless method avoids surface disruption.

Bore Pit Requirements: Launch pit length: Casing length + 20 ft (minimum) Launch pit depth: Invert elevation + 3 ft working room Receiving pit: 10 ft minimum length Typical Bore Lengths: Highway: 60-120 ft (2-lane to 4-lane divided) Railroad: 50-100 ft (single to double track) Maximum bore: ~300 ft for conventional auger bore

Horizontal Directional Drilling (HDD)

A steerable drill creates a curved bore path beneath the crossing. The product pipe is pulled back through the bore after reaming to final diameter. HDD is preferred for long crossings, river crossings, and environmentally sensitive areas.

HDD Design Parameters: Entry angle: 8-18 degrees (typical) Exit angle: 5-12 degrees (typical) Minimum bend radius: 100 ft per inch of pipe diameter Minimum depth: 15 ft below feature (rivers) or 5 ft below bottom Typical Applications: River crossings: 200-3,000+ ft Major highway crossings: 300-800 ft Wetland/environmental crossings: 500-5,000+ ft

Installation Method Comparison

Method Length Range Pipe Size Best For
Open Cut Any Any Low-traffic roads, new construction
Bore & Jack 30-300 ft 4"-48" Roads and railroads, cased crossings
HDD 200-5,000+ ft 2"-48" Rivers, wetlands, long crossings
Microtunneling 100-1,000 ft 24"-120" Large diameter, hard rock

3. Marston Load Theory

Marston load theory, developed by Anson Marston at Iowa State University in the early 1900s, provides the foundation for calculating earth loads on buried conduits. The theory accounts for the relative settlement of the backfill prism directly above the pipe compared to the adjacent undisturbed soil.

Trench Condition (Marston)

Marston Trench Load: W_d = C_d × γ × B_d² Where: W_d = Earth load per unit length (lb/ft) C_d = Load coefficient (dimensionless) γ = Unit weight of backfill (lb/ft³) B_d = Trench width at top of pipe (ft) Load Coefficient: C_d = (1 - e^(-2Kμ'H/B_d)) / (2Kμ') Where: K = Rankine lateral earth pressure ratio μ' = Coefficient of friction (soil on trench wall) H = Depth of cover (ft) Kμ' = 0.110 for granular backfill (typical) Kμ' = 0.130 for saturated clay Kμ' = 0.150 for saturated sand

Embankment Condition (Marston-Spangler)

For pipelines beneath embankments or fill, the load depends on the projection ratio and settlement ratio of the pipe relative to the surrounding soil.

Positive Projecting Embankment: W_c = C_c × γ × D_c² Where: W_c = Earth load per unit length (lb/ft) C_c = Load coefficient for embankment D_c = Outside diameter of pipe or casing (ft) The embankment load coefficient C_c depends on: - H/D_c ratio (depth-to-diameter) - Settlement ratio (r_sd) - Projection ratio (p) For rigid pipes: r_sd × p typically 0.5-1.0 For flexible pipes: r_sd × p typically -0.3 to 0

Prism Load (Simplified)

For preliminary analysis, the prism load provides a straightforward upper-bound estimate of the earth load:

Prism Earth Load: W_p = γ × H × D Where: W_p = Prism load per unit length (lb/ft) γ = Soil unit weight (typically 120 lb/ft³) H = Depth of cover to top of pipe (ft) D = Pipe outside diameter (ft) Example (24" pipe, 5 ft cover): W_p = 120 × 5 × 2.0 = 1,200 lb/ft The prism load assumes no arching effect and is conservative for trench installations but may underestimate loads for positive projecting conditions.

Earth Load Summary by Condition

Installation Type Arching Effect Load vs Prism Load Typical Crossing Use
Narrow trench Positive (beneficial) Less than prism Open-cut road crossings
Wide trench Minimal Approaches prism Shallow installations
Positive projecting Negative (increases load) Greater than prism Embankment crossings
Bore installation Significant positive Much less than prism Bored road/rail crossings

4. API 1102 Analysis

API Recommended Practice 1102 provides the methodology for evaluating steel pipelines crossing highways and railroads. The standard addresses combined earth load, live load, and internal pressure effects on the carrier pipe.

Live Load Models

Loading Axle Load Wheel Config Application
AASHTO H-20 32,000 lb Dual wheels Standard highway design
AASHTO HL-93 32,000 lb + lane load Dual wheels + 640 plf Current LRFD highway design
Cooper E-80 80,000 lb Four axles per truck Standard railroad design
Off-Highway Varies (up to 200,000 lb) Single or tandem Mining, construction equipment

Live Load Distribution (Boussinesq)

Boussinesq Point Load Distribution: σ_z = (3P / 2πH²) × [1 / (1 + (r/H)²)]^(5/2) Where: σ_z = Vertical stress at depth H below surface (psi) P = Concentrated wheel load (lb) H = Depth of cover (ft) r = Horizontal distance from load point (ft) For shallow cover (H < 3 ft), the live load pressure on the pipe can exceed the tire contact pressure. Impact factor I_f must be applied: Highway: I_f = 1.50 (typical) Railroad: I_f = 1.75 (typical, varies with speed)

API 1102 Stress Checks

API 1102 evaluates the carrier pipe for circumferential stress, through-wall bending stress, and combined stress under the combined loading condition.

Circumferential Stress (Combined): σ_c = σ_cp + σ_ce + σ_cl Where: σ_cp = Circumferential stress from internal pressure = P × D / (2t) (Barlow) σ_ce = Circumferential stress from earth load σ_cl = Circumferential stress from live load Through-Wall Bending Stress: σ_bw = K_b × E × (D/t) × (Δy / D) Where: K_b = Bending stress coefficient E = Modulus of elasticity (psi) D = Pipe outside diameter (in) t = Wall thickness (in) Δy = Vertical deflection (in) Allowable Stress Criteria: Circumferential: σ_c ≤ 0.90 × SMYS Combined: Determined by interaction formula

Pipe Deflection (Iowa Formula)

Modified Iowa (Spangler) Deflection Formula: Δy = D_l × K × (W_c + W_l) / (EI/r³ + 0.061E') Where: Δy = Vertical pipe deflection (in) D_l = Deflection lag factor (1.0-1.5) K = Bedding constant (0.083-0.110) W_c = Earth load (lb/in of pipe length) W_l = Live load (lb/in of pipe length) EI/r³ = Pipe stiffness factor E' = Modulus of soil reaction (psi) Typical E' values: Dumped native soil: 200-400 psi Compacted granular: 1,000-2,000 psi Compacted select fill: 2,000-3,000 psi

5. Cased vs Uncased Design

The decision to use a cased or uncased crossing involves engineering, regulatory, and economic factors. Industry practice has evolved significantly, with modern standards generally favoring uncased crossings for steel pipelines when properly designed.

Cased Crossing Design

In a cased crossing, the carrier pipe is installed inside a larger-diameter steel casing pipe. Insulating spacers maintain annular clearance and prevent metallic contact between the carrier and casing.

Casing Pipe Sizing: Casing ID ≥ Carrier OD + 2 × spacer height + clearance Typical sizing rule of thumb: Casing nominal size = Carrier nominal size + 2 to 4 sizes Example: 12" carrier pipe Minimum casing: 16" (tight fit with spacers) Typical casing: 18" or 20" (allows insertion) Spacer Requirements: Material: Dielectric (polyethylene, phenolic) Spacing: 8-20 ft intervals (per pipe diameter) Width: 6-12 inches Support angle: 120-degree cradle minimum

Uncased Crossing Design

Uncased crossings install the carrier pipe directly in the soil without a casing. This approach allows cathodic protection to function properly and eliminates the corrosion risks associated with casing-carrier annulus water accumulation.

Uncased Crossing Advantages: - Cathodic protection operates effectively - No casing-carrier annulus corrosion concern - Lower installed cost (no casing material) - Easier inline inspection (no casing interference) - Simpler installation Uncased Crossing Requirements: - Heavier wall pipe (increased wall thickness) - Select backfill with controlled compaction - External coating must withstand installation loads - Additional depth of cover may be required - Concrete coating or markers for third-party protection

Comparison Matrix

Factor Cased Crossing Uncased Crossing
Cathodic protection Shielded (problematic) Fully effective
Corrosion risk Annulus water trapping Standard external corrosion
Installation cost Higher (casing + spacers) Lower (single pipe)
Inline inspection May cause signal interference No interference
Structural protection Casing carries external loads Carrier must be designed for loads
Regulatory Required by some state DOTs Permitted by PHMSA/DOT 192
Industry trend: PHMSA and NACE (now AMPP) have published guidance indicating that cased crossings can create long-term integrity challenges due to shielding of cathodic protection and trapped moisture in the annulus. Many operators now prefer uncased crossings for new construction when permitted by the crossing authority.

6. DOT 49 CFR 192 Requirements

Title 49 of the Code of Federal Regulations Part 192 establishes minimum safety standards for gas pipeline crossings. Requirements vary based on class location, crossing type, and pipeline operating parameters.

Minimum Cover Requirements (192.327)

Location Class 1 Class 2 Class 3 & 4
Normal soil 30 in 30 in 30 in
Consolidated rock 18 in 18 in 24 in
Under roads (public) 36 in 36 in 36 in
Under railroads 36 in below ties 36 in below ties 36 in below ties
Under drainage ditches 36 in 36 in 36 in

Design Factor Requirements (192.111)

Maximum Operating Pressure (Barlow): P = (2 × S × t × F × E × T) / D Where: P = Maximum allowable operating pressure (psig) S = Specified minimum yield strength (psi) t = Nominal wall thickness (in) F = Design factor (class-dependent) E = Longitudinal joint factor (1.0 for seamless/ERW) T = Temperature derating factor (1.0 below 250°F) D = Pipe outside diameter (in) Design Factors at Crossings: Highway crossings: Same as adjacent class location Railroad crossings: 0.60 maximum (most conservative) Class 1: F = 0.72 Class 2: F = 0.60 Class 3: F = 0.50 Class 4: F = 0.40

Additional 192 Requirements

Key Regulatory Requirements: 192.325 – Design of underground crossings - Must withstand anticipated external loads - Casing or increased wall thickness required 192.327 – Cover requirements (table above) 192.329 – Casing requirements (if casing is used) - Sealed at both ends - Electrically isolated from carrier pipe - Vented (optional, debated in industry) 192.461 – External corrosion control - Cathodic protection required - Casing must not shield CP current 192.612 – Inspections at crossings - Periodic patrol and leak surveys - Depth verification after ground disturbance

7. Practical Considerations

Crossing Agreement and Permitting

Pipeline crossings require permits and crossing agreements from the authority having jurisdiction. These agreements specify construction methods, pipe specifications, restoration requirements, and ongoing maintenance responsibilities.

Plan early: Railroad crossing permits can take 6-12 months to obtain. State DOT permits for highway crossings typically require 30-90 days. Begin the permitting process well before construction is scheduled.

Cathodic Protection at Crossings

Cathodic protection requires special attention at crossings. Cased crossings can create shielding problems where the casing blocks protective current from reaching the carrier pipe. Test leads should be installed on both the carrier and casing to monitor CP effectiveness.

CP Consideration Cased Crossing Uncased Crossing
Current distribution Shielded by casing Normal distribution
Test leads On carrier AND casing Standard test station
Isolation Spacers prevent contact Not applicable
Annulus monitoring Vent pipes for inspection Not applicable

Backfill and Compaction

Backfill Requirements at Crossings: Road crossings: - Controlled low-strength material (CLSM/flowable fill) - Or granular backfill compacted to 95% Standard Proctor - Pavement restoration to DOT specifications Railroad crossings: - Granular backfill compacted in 6-inch lifts - Replace ballast to original depth and profile - Restore drainage and sub-ballast layers Open-cut river crossings: - Weight coating or concrete blanket for buoyancy - Rock armor or riprap for scour protection - Minimum 4 ft cover below stable streambed

Marker and Warning Requirements

All pipeline crossings must be marked in accordance with 49 CFR 192.707. Markers must identify the pipeline operator, emergency phone number, and indicate the presence of a high-pressure pipeline. Additional crossing-specific markers are required at each side of roads and railroads.

Inspection and Monitoring

Pipeline crossings represent concentrated risk locations and warrant additional inspection attention in the operator's integrity management program:

  • Aerial or ground patrol at crossings during routine surveillance
  • Depth-of-cover surveys after flooding, erosion, or road reconstruction
  • Close interval survey (CIS) for cathodic protection verification at cased crossings
  • Inline inspection (ILI) analysis focused on crossing segments
  • Leak survey concentration at crossing locations
  • Casing vent monitoring for presence of gas (indicates carrier leak)