Line Sizing

Engineering fundamentals for pipe diameter selection

1. Sizing Principles

Line sizing balances capital cost (larger pipe = more expensive) against operating cost (smaller pipe = higher pressure drop = more compression/pumping energy). Key constraints include velocity limits, pressure drop, and erosion.

Sizing Criteria

Criterion Concern Limit
Maximum velocity Erosion, noise, vibration Service-dependent (see tables)
Minimum velocity Liquid holdup, solids deposition 3–5 ft/s liquids; varies for gas
Pressure drop Available pressure, compression cost 0.5–2 psi/100 ft typical
Noise Personnel safety, equipment damage <85 dBA at 1m

Basic Velocity Equation

Gas: V = 0.4087 × (Q × Z × T) / (P × D²) Where: V = Velocity (ft/s) Q = Flow rate (MMSCFD) Z = Compressibility factor T = Temperature (°R) P = Pressure (psia) D = Inside diameter (inches) Liquid: V = 0.4085 × Q / D² Where: V = Velocity (ft/s) Q = Flow rate (GPM) D = Inside diameter (inches)

2. Gas Line Sizing

Erosional Velocity

The maximum velocity to prevent pipe wall erosion, especially with entrained liquids or solids:

API RP 14E Erosional Velocity: V_e = C / √ρ Where: V_e = Erosional velocity (ft/s) C = Empirical constant (100–150 typical) ρ = Gas density at flowing conditions (lb/ft³) C-factor guidelines: C = 100: Continuous service, solids present C = 125: Intermittent service, clean gas C = 150: Clean, dry gas, non-corrosive C = 200: Very clean service (sometimes used)

Recommended Gas Velocities

Service Velocity (ft/s) Notes
Compressor suction 30–50 Low ΔP critical
Compressor discharge 50–80 Higher density
Process headers 60–100 General rule
Transmission pipelines 20–50 Long distance, optimize ΔP
Flare headers 0.3–0.5 Mach Noise, backpressure limits
Relief valve inlet <3% ΔP Per API 520

Pressure Drop Approach

For long pipelines, size based on allowable pressure drop:

Target pressure drop: Gathering lines: 5–20 psi/mile Transmission: 1–5 psi/mile Plant piping: 0.5–2 psi/100 ft Solve for D using flow equations (Panhandle, Weymouth, etc.)
📊 Gas Line Sizing Chart
Nomograph or chart with: X-axis: Flow rate (MMSCFD, log scale 0.1 to 100). Y-axis: Pipe ID (inches, 2" to 24"). Family of curves for different velocities (30, 60, 100 ft/s) at reference pressure (say 500 psia). Overlay erosional velocity limit (red dashed line). User can read pipe size for given flow and velocity constraint.

3. Liquid Line Sizing

Recommended Liquid Velocities

Service Velocity (ft/s) Notes
Pump suction 3–5 NPSH critical; minimize friction
Pump discharge 6–10 Higher velocity acceptable
Gravity flow 1–3 Depends on available head
Process lines (general) 5–8 Balance cost vs. ΔP
Crude oil pipelines 3–7 Optimize for energy cost
Water service 5–10 Cooling water, utility
Slurries >5 Keep solids suspended

Minimum Velocity

Prevent settling of solids or accumulation of gas pockets:

Quick Sizing Formula

Approximate pipe diameter: D = √(0.4085 × Q / V) Example: Q = 500 GPM, V = 6 ft/s D = √(0.4085 × 500 / 6) = √34.0 = 5.8" → Use 6" Schedule 40 (ID = 6.065")

4. Two-Phase Considerations

Two-phase (gas-liquid) lines require special attention for flow regime, liquid holdup, and slug formation.

API RP 14E for Two-Phase

Mixture velocity: V_m = V_sg + V_sl Erosional velocity (two-phase): V_e = C / √ρ_m ρ_m = (W_L + W_G) / (W_L/ρ_L + W_G/ρ_G) Where: V_sg, V_sl = Superficial gas, liquid velocities W_L, W_G = Mass flow rates (lb/hr) ρ_L, ρ_G = Densities (lb/ft³)

Slug Flow Considerations

⚠ Slug catcher sizing: Two-phase gathering lines can produce slugs of 100–1000+ barrels. Size inlet separators and slug catchers for worst-case liquid volume using dynamic simulation.

Flow Regime Guidance

Regime Characteristics Design Impact
Stratified Gas on top, liquid on bottom Corrosion at bottom; pigging needed
Slug Alternating liquid plugs and gas Slug catcher required; vibration
Annular Gas core, liquid film on wall Generally acceptable; high velocity
Mist Liquid droplets in gas Erosion concern; entrainment

5. Economic Optimization

Optimal pipe size minimizes total cost = capital cost + operating cost (NPV basis).

Cost Components

Component Effect of Larger Pipe
Pipe material Increases (more steel)
Installation (trenching, welding) Increases
Valves, fittings Increases
Compression/pumping energy Decreases (lower ΔP)
Compressor/pump size Decreases
📈 Economic Pipe Diameter
Graph showing: X-axis: Pipe diameter (inches). Y-axis: Annualized cost ($/year). Three curves: (1) Capital cost (increasing with diameter), (2) Operating cost/energy (decreasing with diameter), (3) Total cost (U-shaped). Mark optimum diameter at minimum of total cost curve. Annotate that larger pipe saves energy but costs more upfront.

Rules of Thumb

Quick Economic Velocity

Peters & Timmerhaus correlation: V_opt = K × ρ^(-0.37) × D^0.13 Typical result for hydrocarbons: Gas: V_opt ≈ 60–100 ft/s Liquid: V_opt ≈ 5–8 ft/s These coincide with typical velocity limits— velocity criteria usually give near-economic sizing.

References