Compressor Foundations

Foundation Grout Volume Calculations

Calculate grout volume requirements for compressor foundations, select between epoxy and cementitious grouts, and plan pours for proper curing and load transfer.

Epoxy Grout

12,000-16,000 psi

High strength; preferred for dynamic loads

Cementitious Grout

5,000-10,000 psi

Lower cost; adequate for static equipment

Grout Thickness

1-3 inches

Typical gap between skid and concrete

1. Overview

Grouting is the process of filling the gap between the equipment base (skid, sole plate, or baseplate) and the concrete foundation. Proper grouting ensures uniform load transfer, vibration damping, and long-term alignment stability for rotating equipment.

Load Transfer

100% Contact

Full bearing between skid and foundation

Vibration Damping

Energy Dissipation

Grout absorbs dynamic forces

Alignment Stability

Prevents Shifting

Locks equipment position permanently

Corrosion Protection

Seals Interface

Prevents moisture intrusion at base

Why grout matters: Inadequate grouting is one of the top causes of compressor vibration problems. Voids in the grout allow the baseplate to flex, creating soft-foot conditions that cause misalignment, bearing damage, and seal failures. Grout quality directly impacts machine reliability.

2. Grout Types

Two primary grout families are used for compressor foundations: epoxy (polymer) grout and cementitious (non-shrink) grout. Selection depends on equipment type, loading conditions, and environmental factors.

Grout Comparison

PropertyEpoxy GroutCementitious Grout
Compressive strength12,000-16,000 psi5,000-10,000 psi
Tensile strength1,500-2,500 psi400-800 psi
Bond to steel1,500-2,000 psi200-500 psi
Bond to concrete1,000-1,500 psi300-600 psi
Chemical resistanceExcellentGood (affected by acids/oils)
Vibration resistanceExcellent (viscoelastic damping)Good (rigid)
Temperature limit150-200 deg F continuous500+ deg F
Working time30-90 min (temp dependent)30-60 min
Material cost$15-$25 per gallon$3-$8 per gallon
ShrinkageMinimal (0.001-0.003 in/in)Non-shrink to slight expansion

Selection Guidelines

ApplicationRecommended GroutReason
Reciprocating compressorEpoxyHigh dynamic loads; superior vibration resistance
Centrifugal compressorEpoxyAlignment sensitivity; excellent bond strength
Gas engine driverEpoxyPulsating loads; thermal cycling
Gas turbine driverEpoxy or cementitiousEpoxy preferred but check temperature limits
Electric motorCementitious or epoxyLower dynamic loads; either acceptable
Pump baseplateEpoxy preferredAlignment-critical; chemical exposure
Structural columnsCementitiousStatic load only; cost-effective
High-temperature (>150 deg F)CementitiousEpoxy loses strength above 150-200 deg F

Common Grout Products

TypeProduct ExamplesYield (ft3/unit)Notes
EpoxyChockfast Orange, Masterflow 6480.3-0.5 ft3/kit3-component mix; aggregate filled
Epoxy (precision)Escoweld 7505, Chockfast Red0.1-0.2 ft3/cartridgeFor chock pads; pour-in-place
CementitiousMasterflow 713, Five Star0.5-0.6 ft3/bagMix with water; aggregate filled
Cementitious (precision)Masterflow 928, Embeco 8850.45-0.55 ft3/bagExtended flow for tight spaces
Industry standard: API 686 (Recommended Practice for Machinery Installation) requires epoxy grout for all rotating equipment foundations where dynamic loads exceed 25% of static loads or where alignment sensitivity requires less than 2 mils tolerance. Most compressor installations fall into this category.

3. Volume Calculations

Accurate volume calculation prevents shortages (which cause cold joints and voids) and excessive waste. Always calculate net volume, then add a waste factor.

Basic Volume Calculation: V_grout = (L x W x T) - V_obstructions Where: V_grout = Net grout volume (cubic feet) L = Length of grout area (ft) W = Width of grout area (ft) T = Thickness (gap between skid and concrete) (ft) V_obstructions = Volume displaced by anchor bolts, sleeves, etc. Anchor Bolt Volume Deduction: V_bolt = N x pi x (D_bolt/2)^2 x T Where: N = Number of anchor bolts D_bolt = Bolt diameter (ft) T = Grout thickness (ft) Bolt Sleeve Volume Deduction: V_sleeve = N x pi x (D_sleeve/2)^2 x T Where D_sleeve = Sleeve outer diameter (typically 2-4x bolt diameter) Conversion: 1 cubic foot = 7.48 gallons V_gallons = V_grout (ft3) x 7.48

Waste and Contingency Factors

FactorEpoxy GroutCementitious GroutNotes
Formwork leakage5-10%5-10%Good forms reduce waste
Mixing loss2-5%2-5%Material left in mixer/buckets
Shoulder/chamfer5-15%5-15%Grout extends beyond skid edge
Surface irregularity5-10%5-10%Chipped concrete, uneven surface
Total contingency20-30%20-30%Order 1.25-1.30x calculated volume

Complex Geometry

Multi-Section Foundation: For compressor skids with varying grout thickness: V_total = Sum of V_i for each section Section types: Rectangular: V = L x W x T L-shaped: Split into two rectangles Tapered: V = L x W x (T1 + T2) / 2 (average thickness) Stepped: Calculate each step separately Chamfer (shoulder) volume: V_chamfer = Perimeter x (chamfer_width x chamfer_height / 2) x L_chamfer Typical chamfer: 45-degree, 1-2 inches wide Prevents edge chipping and concentrates load inward. Header Box / Forming Volume: V_header = L_header x W_header x T Add header box volume if grout fills forming beyond the skid.
Grout thickness limits: Minimum grout thickness is 1 inch (25 mm) to ensure proper flow and consolidation. Maximum thickness for a single pour is typically 4-6 inches for epoxy (exotherm limits) and 6-8 inches for cementitious. Thicker pours require staged placement or aggregate extension.

4. Pour Planning

Grout pour planning ensures continuous placement without cold joints, adequate working time, and proper crew sizing. A failed pour can require complete removal and re-grouting at significant cost.

Pour Sequence

StepActivityDurationCritical Notes
1Surface preparation1-2 daysChip laitance; SSD condition for cementitious
2Formwork installation4-8 hoursSeal all joints; allow for head pressure
3Pre-pour inspection1-2 hoursCheck alignment, bolt torque, cleanliness
4Material staging2-4 hoursCondition to pour temperature range
5Mixing and placement30-90 minContinuous pour; no interruptions
6Initial cure4-24 hoursNo vibration; maintain temperature
7Form removal24-72 hoursAfter reaching minimum strength
8Full cure3-7 daysBefore equipment operation

Crew and Equipment

Mixing Rate Estimation: For epoxy grout: One mixer (5-gallon capacity) produces ~0.5 ft3 per batch Batch cycle time: 5-8 minutes (mix, pour, reload) One mixer crew: 4-6 ft3/hour For cementitious grout: One mixer (mortar mixer) produces 2-3 ft3 per batch Batch cycle time: 5-10 minutes One mixer crew: 12-18 ft3/hour Number of Mixers Required: N_mixers = V_total / (Rate_per_mixer x Working_Time) Where Working_Time accounts for grout pot life: Epoxy at 75 deg F: 30-45 minutes working time Epoxy at 90 deg F: 15-25 minutes working time Cementitious: 30-45 minutes working time Crew Sizing: Per mixer: 2-3 workers (1 mixing, 1-2 placing) Supervisor: 1 per pour QC inspector: 1 per pour (verify placement, sample) Total crew for large pour: 6-12 workers

Pour Direction

MethodDescriptionBest For
One-side pourPour from one side; grout flows to opposite sideNarrow baseplates (< 4 ft wide)
Center pourPour at center; grout flows outwardWide baseplates with center access
Multi-point pourPour from several locations simultaneouslyLarge pours exceeding pot life
Head-box pourUse elevated reservoir to provide head pressureLong flow distances; tight gaps
Head pressure rule: For epoxy grout, the grout head (height in the header box above the skid) should be at least 1.5 times the flow distance. For a 6-foot flow distance under a skid, maintain at least 9 inches of head. This ensures complete filling without voids.

5. Temperature Considerations

Temperature is the most critical variable in grouting operations. It affects working time, exotherm, cure rate, and final properties. Both ambient and material temperatures must be controlled.

Temperature Limits

ConditionEpoxy GroutCementitious Grout
Minimum pour temp40-50 deg F40-50 deg F
Maximum pour temp90-95 deg F90-100 deg F
Ideal pour temp65-80 deg F60-80 deg F
Foundation temp (min)50 deg F40 deg F
Foundation temp (max)90 deg F100 deg F
Exotherm peak (deep pour)200-350 deg F120-180 deg F
Max continuous service150-200 deg F500+ deg F

Exotherm Management

Epoxy Grout Exotherm: The exothermic curing reaction generates significant heat. Peak temperature depends on: Pour thickness (thicker = higher peak) Ambient temperature (warmer = faster reaction) Grout volume (larger mass retains more heat) Rules of Thumb: 2-inch thickness: Peak exotherm ~150-180 deg F 4-inch thickness: Peak exotherm ~200-250 deg F 6-inch thickness: Peak exotherm ~250-350 deg F Maximum Allowable Exotherm: 350 deg F (above this, grout may crack or delaminate) Mitigation Strategies: 1. Pour in cooler ambient (early morning, evening) 2. Pre-cool materials in air-conditioned storage 3. Use extended-work-time formulations 4. Add aggregate extenders (per manufacturer limits) 5. Pour in multiple lifts (2-3 inch maximum per lift) 6. Pre-cool concrete with water evaporation

Cold Weather Grouting

Temperature RangeAction RequiredNotes
> 50 deg FNormal proceduresNo special measures needed
40-50 deg FPre-heat materials; insulate formsSlow cure; extend form time
32-40 deg FHeated enclosure requiredMaintain 50 deg F minimum for 72 hrs
< 32 deg FDo not pourFreeze damage destroys grout integrity

Hot Weather Grouting

Temperature RangeAction RequiredNotes
< 85 deg FNormal proceduresStandard working time available
85-95 deg FPre-cool materials; shade work areaWorking time reduced 30-50%
95-100 deg FEarly morning/evening pour onlyCool foundation with wet burlap
> 100 deg FPostpone or use special formulationsExotherm risk; rapid set
Material conditioning: Store grout materials at 65-75 deg F for at least 24 hours before the pour. Cold epoxy components are viscous and difficult to mix. Hot components have shortened working time and higher exotherm. Air-conditioned storage trailers are standard practice for large grouting projects.

6. Surface Preparation

Surface preparation is the single most important factor in grout bond quality. Poor preparation causes delamination, voids, and eventual equipment vibration problems.

Concrete Surface Preparation

StepMethodAcceptance Criteria
Remove laitanceChipping hammer, bush hammer, or needle scalerExpose aggregate; ICRI CSP 5-7
Remove contaminantsSolvent wipe, degreasingNo oil, grease, or curing compound
Roughen surfaceMechanical profiling1/4-inch amplitude minimum
Clean debrisCompressed air, vacuumNo loose particles or dust
Moisture condition (cementitious)Saturated surface dry (SSD)Dark surface, no standing water
Moisture condition (epoxy)Dry surfaceNo visible moisture; test with plastic sheet

Steel Surface Preparation

StepMethodStandard
Remove mill scaleAbrasive blasting or power toolSSPC-SP6 or SP10
Remove paint/coatingsAbrasive blastingNo coatings in grout contact area
Remove oil/greaseSolvent cleaningSSPC-SP1
Surface profileAngular abrasive blast2-3 mil profile for epoxy bond
Time limitPour within 4-8 hours of blastingBefore flash rust forms
Critical inspection point: The concrete surface must be inspected immediately before pouring. Any moisture (for epoxy), oil spots, or loose material will cause bond failure. Use a flashlight at a low angle to check for surface irregularities and contamination. Document the inspection with photographs.

7. Worked Examples

Example 1: Rectangular Skid Grout Volume

Given: Compressor skid: 20 ft long x 8 ft wide Grout thickness: 2 inches (0.167 ft) Number of anchor bolts: 16 Bolt diameter: 1.5 inches (0.125 ft) Bolt sleeve OD: 4 inches (0.333 ft) Chamfer: 45 deg, 1.5 inches wide all around Step 1: Gross volume V_gross = 20 x 8 x 0.167 = 26.67 ft3 Step 2: Anchor bolt deductions V_bolts = 16 x pi x (0.125/2)^2 x 0.167 = 16 x 0.00204 = 0.033 ft3 V_sleeves = 16 x pi x (0.333/2)^2 x 0.167 = 16 x 0.01454 = 0.233 ft3 Total deduction = 0.033 + 0.233 = 0.266 ft3 Step 3: Chamfer volume Perimeter = 2 x (20 + 8) = 56 ft V_chamfer = 56 x (1.5/12 x 1.5/12 / 2) = 56 x 0.0078 = 0.44 ft3 Step 4: Net grout volume V_net = 26.67 - 0.27 + 0.44 = 26.84 ft3 Step 5: Apply contingency (25%) V_order = 26.84 x 1.25 = 33.6 ft3 Step 6: Convert to gallons V_gallons = 33.6 x 7.48 = 251 gallons Step 7: Number of kits (assuming 0.4 ft3/kit for epoxy) N_kits = 33.6 / 0.4 = 84 kits

Example 2: Working Time and Crew Sizing

Given: Total grout volume: 33.6 ft3 (from Example 1) Grout type: Epoxy (Chockfast Orange) Ambient temperature: 85 deg F Working time at 85 deg F: 25 minutes Mixing rate per mixer: 5 ft3/hour Step 1: Required mixing rate Must complete pour within working time. Required rate = 33.6 ft3 / (25/60 hr) = 80.6 ft3/hr Step 2: Number of mixers N_mixers = 80.6 / 5 = 16.1 -> 17 mixers minimum This is impractical. Solutions: a) Reduce ambient temperature (pour in early morning) b) Pre-cool materials to 65 deg F (extends working time to 40 min) c) Divide into multiple pours with construction joints Step 3: Revised plan at 65 deg F material temp Working time at 65 deg F: ~45 minutes Required rate = 33.6 / (45/60) = 44.8 ft3/hr N_mixers = 44.8 / 5 = 9.0 -> 10 mixers Step 4: Crew sizing 10 mixers x 2 workers = 20 workers + 1 supervisor + 1 QC Total crew: 22 workers Alternative: Two-pour approach Pour 1: Front half (16.8 ft3) with 5 mixers in 40 min Pour 2: Back half (16.8 ft3) with 5 mixers in 40 min Total crew: 12 workers per pour (much more manageable)

Example 3: Material Cost Comparison

Given: Grout volume required: 33.6 ft3 (251 gallons) Epoxy Grout: Cost: $20/gallon average (mixed with aggregate) Material cost = 251 x $20 = $5,020 Kits to order: 84 kits at ~$60/kit = $5,040 Cementitious Grout: Cost: $5/gallon average Material cost = 251 x $5 = $1,255 Bags to order: 33.6 / 0.5 = 68 bags at ~$25/bag = $1,700 Cost ratio: Epoxy is ~3-4x more expensive in material. However, total installed cost difference is smaller because: Labor cost is similar for both types Epoxy requires less surface prep (no SSD conditioning) Cementitious requires longer cure time (higher schedule cost) Epoxy repairs are less frequent over equipment lifetime Lifetime value: For a $2M compressor package with 25-year design life, the $3,500 grout cost premium for epoxy is negligible compared to the reliability benefits.