Pipeline Maintenance

Flow Hot Tapping Operations

Design hot tap connections, calculate flow effects during tapping, and implement safe procedures for installing fittings on pressurized pipelines without shutdown.

Pressure limit

80% SMYS max

ASME B31.8: Hot tapping limited to 80% SMYS to prevent burn-through risk.

Minimum thickness

0.250" + CA

ASME requires 0.250" minimum wall thickness plus corrosion allowance for hot taps.

Velocity limit

< 10 ft/s liquid

Flow velocity must be reduced (<10 ft/s liquid, <60 ft/s gas) to prevent cutter damage.

Use this guide when you need to:

  • Design hot tap fittings for pressurized pipelines.
  • Calculate flow effects during tapping operations.
  • Develop safe hot tapping procedures.

1. Overview & Applications

Hot tapping (pressure tapping, line tapping) installs a branch connection on a pipeline while the line remains in service under pressure. Critical for:

Service continuity

No shutdown required

Avoids production losses (thousands to millions of dollars per day).

New connections

Branch installations

Add meter runs, sample points, pig launchers, relief valves to existing lines.

Line isolation

Valve insertions

Install block valves using hot tap machines for future maintenance isolation.

Repairs

Stopple insertions

Isolate damaged sections for repair without draining/depressurizing entire line.

Image: Hot Tap Assembly Diagram
Cross-section showing hot tap machine, split-tee fitting, isolation valve, cutter, pilot drill, and coupon retention mechanism on pressurized pipeline.

Key Concepts

  • Hot tap machine: Mechanical device that cuts opening while sealed to pipeline via bolted fitting
  • Fitting: Welded or mechanical attachment providing branch connection for tapping machine
  • Coupon: Circular piece of pipe wall removed by hot tap cutter
  • Stopple: Line plug inserted through hot tap to isolate pipeline section
  • Completion plug: Blind flange or cap installed after tapping machine is removed
Why hot tapping is used: Shutting down a major transmission pipeline can cost $100k-$1M+ per day in lost revenue, plus disruption to downstream customers. Hot tapping allows modifications and connections with zero downtime, paying for itself (typically $20k-100k operation cost) in hours to days of avoided shutdown.

Hot Tap Applications

Application Typical Size Purpose
Sample point 1/2" to 2" Gas quality sampling, liquid analysis
Pressure gauge/transmitter 1/2" to 1" Pressure monitoring, SCADA integration
Blowdown connection 2" to 6" Emergency depressurization capability
Meter run 4" to 24" Add measurement/metering to existing line
Pig launcher/receiver 6" to 36" (match line size) Install pigging facilities for cleaning/inspection
Block valve insertion Equal to line size Future isolation capability, hot tap machine inserts full-opening valve
Pipeline tie-in 4" to 48" Connect new pipeline to existing without shutdown

Limitations and Exclusions

  • ASME B31.8 (gas): Hot tapping permitted if hoop stress ≤ 80% SMYS, wall thickness ≥ 0.250" + corrosion allowance
  • ASME B31.4 (liquid): Similar limits, plus restrictions on flammable liquids above flash point
  • Material restrictions: No hot tapping on brittle materials (cast iron), heat-sensitive coatings, or unknown metallurgy
  • Condition restrictions: No hot tapping on corroded pipe (wall loss > 10%), dented/damaged pipe, or areas with active leaks
  • Environmental restrictions: Not permitted in some environmentally sensitive areas without special approval

2. Hot Tap Fitting Design

Hot tap fittings must withstand full pipeline pressure plus welding thermal effects without failure.

Image: Split-Tee Fitting Components
Exploded view showing two half-shells, branch outlet, reinforcing saddle, seal welds (fillet and circumferential), and bolt pattern for assembly.

Welded Split-Tee Fitting

Full-Encirclement Split-Tee Design: Most common for permanent hot taps. Components: - Two half-shells (split-tee) matching pipe curvature - Branch outlet (size of hot tap) - Reinforcing pad (optional, for large branch-to-run ratios) - Seal weld (full-penetration fillet welds) Material requirements: - Match pipe material (API 5L grade, strength) - Weldable per ASME Section IX - Impact tested if required for service temperature Typical specifications: Run pipe: 12" × 0.375" wall, Grade X52 Branch: 6" hot tap (outlet) Fitting: ASTM A234 WPB (wrought steel) Design pressure: 1,200 psig Design temperature: 150°F Wall thickness requirement for branch: t_branch = (P × D) / (2 × S × E + P) Where: P = Design pressure (1,200 psig) D = Branch OD (6.625") S = Allowable stress (35,000 psi for A234 WPB at 150°F) E = Weld joint efficiency (1.0 for full-encirclement) t_branch = (1,200 × 6.625) / (2 × 35,000 × 1.0 + 1,200) t_branch = 7,950 / 71,200 t_branch = 0.112" Use Schedule 40 branch (0.280" wall) ✓ Adequate

Reinforcement Calculations (ASME B31.8)

Area Replacement Method: When branch diameter > 1/3 of run diameter, reinforcement required. Area removed from run pipe: A_removed = d × t_run Where: d = Diameter of opening (branch ID) t_run = Run pipe wall thickness Area provided by branch: A_branch = 2 × t_branch × (H - t_run) Where: t_branch = Branch wall thickness H = Height of branch above run pipe surface (typically 2× t_branch minimum) Area provided by run pipe excess: A_run = 2 × L × (t_run - t_min) Where: L = Reinforcement zone length (typically 2.5 × √(D × t_run)) t_min = Minimum required wall thickness for pressure Reinforcement adequacy: A_branch + A_run + A_pad ≥ A_removed If insufficient, add reinforcing pad (split saddle). Example: Run pipe: 12" (12.75" OD) × 0.375" wall Branch: 6" (6.625" OD) × 0.280" wall Opening diameter: 6.065" (branch ID) A_removed = 6.065 × 0.375 = 2.274 in² A_branch = 2 × 0.280 × (0.560 - 0.375) = 0.104 in² A_run = 2 × 8.7" × (0.375 - 0.250) = 2.175 in² Total available = 0.104 + 2.175 = 2.279 in² ✓ Adequate (exceeds 2.274 in²) No reinforcing pad required.

Mechanical Fittings

Alternative to welded fittings for temporary taps or non-weldable pipes:

Fitting Type Pressure Rating Advantages Limitations
Split-bolt saddle (stainless band) Up to 300 psig No welding, quick install, removable Low pressure only, potential leak path
Bolted split-tee with gasket Up to 600 psig No hot work, suitable for coated pipe Requires smooth pipe surface, frequent inspection
Compression-seal fitting Up to 1,500 psig High pressure, no welding, leak-proof Expensive, requires specialized installation tools

Welding Procedure Qualification (WPQ)

ASME Section IX Requirements: Hot tap welds are considered critical (high consequence of failure). Welding requirements: 1. Procedure Qualification Record (PQR) - Qualified per ASME Section IX - Essential variables: base metal, filler metal, position, heat input 2. Welder Performance Qualification (WPQ) - Welders tested on similar joint configuration - Valid for 6 months of continuous work 3. Heat input control: - Preheat required if carbon equivalent (CE) > 0.40 - Interpass temperature < 500°F typical - PWHT (post-weld heat treatment) usually not required for hot taps 4. Non-destructive examination (NDE): - Visual inspection (100% of welds) - Magnetic particle (MT) or liquid penetrant (PT): 100% of completed welds - Radiographic (RT) or ultrasonic (UT): 10-25% per company specs Typical welding process: - SMAW (stick) for root and fill passes - FCAW (flux-core) or GMAW (MIG) for fill/cap (higher productivity) - Low-hydrogen electrodes (E7018 or equivalent) Consumable insert (if used): - Pre-placed backing ring for root pass - Improves weld quality, reduces burn-through risk - ASME approved inserts only

Fitting Installation Sequence

Welded Fitting Installation Steps: 1. Surface preparation: - Blast clean pipe surface to white metal (SSPC-SP-10) - Remove coating 6" beyond fitting footprint - UT inspect pipe wall thickness (verify adequate, no corrosion) - Check for dents, buckles, welds within fitting zone (relocate if present) 2. Fitting alignment: - Position split-tee halves around pipe - Verify branch perpendicular to run (±2° tolerance) - Bolt halves together (finger-tight) - Check fit-up gaps (< 1/8" typical) 3. Tack welding: - Apply 2-4 tack welds to hold fitting in place - Remove assembly bolts 4. Seal welding: - Weld both longitudinal seams (where halves meet) - Weld circumferential fillet at pipe OD - Multi-pass welding (3-6 passes typical for 1/4" fillet) - Control heat input (max 30 kJ/in per pass typical) 5. Cooling: - Allow natural air cooling (do not quench) - Monitor cooling rate with temp sticks 6. NDE: - MT or PT of completed welds - RT or UT if specified 7. Pressure test: - Hydro or pneumatic test to 1.5× design pressure - Hold 10 minutes, no leaks 8. Install valve and hot tap machine
Burn-through prevention: Burn-through (welding arc penetrates pipe wall, causing leak) is the primary risk during fitting installation. Mitigation: Use qualified welders, control heat input (max 25-30 kJ/in), maintain flow if possible (internal cooling), monitor temperature (temp sticks on inside if accessible).

3. Flow Rate Effects During Tapping

Flow velocity affects cutter performance, chip removal, and coupon extraction forces.

Image: Flow Velocity Effects on Cutter
Side-view diagram showing pipeline flow direction, cutter orientation, flow deflection forces, chip evacuation path, and coupon extraction direction with velocity vectors.

Velocity Limits for Hot Tapping

Maximum Allowable Velocities: Liquid service (oil, water, condensate): V_max = 10 ft/s (3 m/s) Basis: Higher velocities can: - Deflect cutter, causing off-center cut - Flush cutting chips into pipeline (not collected in machine) - Require excessive force to extract coupon - Damage cutter teeth Gas service: V_max = 60 ft/s (18 m/s) Basis: Gas has lower momentum, less effect on cutter. However, high velocities can: - Create excessive noise/vibration - Erode cutter (if sand/solids present) - Increase risk of ignition (friction heating) Velocity calculation: V = Q / A Where: V = Velocity (ft/s) Q = Volumetric flow rate (ft³/s) A = Pipe cross-sectional area (ft²) Example - Gas line: Flow rate: 50 MMscfd Pressure: 800 psia Temperature: 80°F Pipe: 12" ID (1.0 ft) Q_actual = Q_std × (P_std / P_actual) × (T_actual / T_std) × Z Q_actual = 50 MMscfd × (14.7/800) × (540/540) × 0.88 / 1,440 min/day Q_actual = 50,000 × 0.01838 × 0.88 / 1,440 Q_actual = 561 acfm = 9.35 acf/s A = π × (1.0)² / 4 = 0.785 ft² V = 9.35 / 0.785 = 11.9 ft/s 11.9 ft/s < 60 ft/s ✓ OK for hot tapping

Flow Reduction Methods

Method Velocity Reduction Applicability
Reduce throughput Proportional to flow rate decrease Best option if operationally feasible (coordinate with control room)
Bypass around tap location Can reduce to near-zero Requires parallel line or temporary piping
Throttle upstream valve Reduces flow, increases upstream pressure Limited by upstream pressure constraints
Install flow restrictor (orifice plate) Creates local low-velocity zone Temporary orifice upstream of tap location
Tap during low-demand period Use nighttime/weekend low flow Seasonal or diurnal flow variation

Coupon Extraction Force

Force Required to Extract Coupon: F_extraction = F_pressure + F_shear + F_drag Where: F_pressure = Pressure differential across coupon F_shear = Remaining material ligament (imperfect cut) F_drag = Fluid drag force Pressure force: F_pressure = P × A_coupon Where: P = Line pressure (psig) A_coupon = Area of coupon (in²) Example - 6" coupon, 1,000 psig: A_coupon = π × (6)² / 4 = 28.3 in² F_pressure = 1,000 × 28.3 = 28,300 lb This is the force hot tap machine must overcome to withdraw coupon. Hot tap machine capacity: Hydraulic cylinder rated force: 50,000-200,000 lb typical For 6" tap at 1,000 psi: 50,000 lb machine adequate Larger taps (12"+) at high pressure may require: - 100,000+ lb capacity machines - Multiple withdrawal attempts (rock coupon to break ligament) - Flow reduction to minimize drag force Drag force (flowing): F_drag = 0.5 × ρ × V² × C_d × A Where: ρ = Fluid density (lb/ft³) V = Velocity (ft/s) C_d = Drag coefficient (1.2 for disk) A = Coupon area (ft²) For gas at 10 ft/s, ρ = 3 lb/ft³: F_drag = 0.5 × 3 × (10)² × 1.2 × (6/12)² = 28 lb (negligible) For liquid at 10 ft/s, ρ = 50 lb/ft³: F_drag = 0.5 × 50 × (10)² × 1.2 × (6/12)² = 469 lb (significant, add to pressure force)

Pressure Drop Through Hot Tap Opening

Temporary Pressure Drop During Tapping: When coupon is partially cut (creating flow restriction), pressure drop increases. ΔP = K × (ρ × V²) / (2 × g_c) Where: K = Loss coefficient (depends on obstruction geometry) ρ = Density V = Velocity g_c = Gravitational constant (32.2 lb·ft/lb_f·s²) For 50% open area (coupon half-cut): K ≈ 10-20 (severe restriction) This pressure drop is temporary (minutes) and localized to tap area. Monitor downstream pressure during tapping: If drop > 10% of normal, pause cutting and allow recovery. Prolonged restriction can trigger: - Pressure alarms - Flow meter errors - Compressor surge (gas lines) Best practice: Brief, intermittent cuts rather than continuous machining.
Flow direction consideration: Orient hot tap perpendicular to flow (not against flow). Tapping into high-velocity flow (head-on) creates extreme forces on cutter and makes coupon extraction difficult. If flow direction varies, perform tap during period when velocity is lowest or flow is in favorable direction.

4. Hot Tapping Procedures

Systematic procedures ensure safe, successful hot tap operations.

Image: Hot Tapping Operation Sequence
Step-by-step diagram showing: (1) Fitting welded to pipe, (2) Valve installed, (3) Hot tap machine mounted, (4) Cutter advancing, (5) Coupon cut complete, (6) Cutter retracted with coupon, (7) Valve closed, (8) Machine removed.

Pre-Tap Planning and Approvals

Engineering Review Checklist: 1. Design calculations: - Confirm hoop stress ≤ 80% SMYS - Verify wall thickness ≥ 0.250" + CA - Calculate reinforcement (if required) - Select fitting and machine size 2. Material verification: - Identify pipe material (grade, vintage) - Check weldability (carbon equivalent) - Review mill certs (tensile, impact, chemistry) - Confirm no brittle materials (cast iron, old ERW) 3. Condition assessment: - UT inspect wall thickness (20+ readings around tap location) - In-line inspection (ILI) data if available - Visual inspect exterior (coating condition, dents, damage) - Corrosion assessment (metal loss < 10%) 4. Operating conditions: - Line pressure (normal, max, min) - Flow rate (current, expected during tap) - Temperature (current, max) - Fluid composition (H₂S content, if any) 5. Location considerations: - Access (equipment, vehicles) - Environmental (wetlands, sensitive areas) - Proximity to other pipelines, utilities - Permit requirements (DOT, EPA, state) 6. Approvals required: - Engineering: Design review, calculations - Operations: Line capacity, flow reduction - Safety: Job Safety Analysis (JSA), Permit to Work - Regulatory: DOT (if interstate), state (if required)

Hot Tapping Procedure (Step-by-Step)

Field Execution Sequence: Day 1 - Fitting Installation: 1. Mobilize equipment and crew (2-4 welders, 1 supervisor) 2. Identify tap location (GPS, stationing, landmarks) 3. Excavate and expose pipe (min 10 ft length) 4. Clean pipe exterior (blast clean) 5. UT measure wall thickness (verify adequate) 6. Install fitting (weld split-tee per WPS) 7. NDE of welds (MT/PT, RT if required) 8. Pressure test fitting (1.5× design pressure) 9. Install isolation valve on branch 10. Backfill excavation (partial, leave fitting exposed) Day 2 - Hot Tapping Operation: 1. Pre-job safety briefing (crew, operations) 2. Verify line conditions (P, T, flow rate) 3. Reduce flow if required (coordinate with control room) 4. Install hot tap machine on branch valve 5. Pressure test hot tap machine (verify seal) 6. Open branch valve (equalize machine with line pressure) 7. Advance cutter to pipe wall (feed slowly) 8. Begin cutting (1-2 RPM rotation, steady feed pressure) 9. Monitor cutting progress (advance indicator, time) 10. Complete cut (cutter breaks through, coupon free) 11. Retract cutter with coupon into machine 12. Close branch valve (isolate coupon in machine) 13. Depressurize machine 14. Remove machine and extract coupon 15. Inspect coupon (verify clean cut, no defects) 16. Install completion plug or new connection 17. Pressure test (verify no leaks) 18. Return line to normal operation Typical duration: - Fitting installation: 8-16 hours (depends on size, access) - Hot tapping operation: 2-6 hours (depends on size, wall thickness, flow) Total project: 2-3 days typical

Hot Tap Machine Setup

Machine Component Function Critical Checks
Pressure chamber Seals to valve, contains coupon Gasket condition, bolt torque, pressure test
Drive mechanism Rotates cutter, provides feed pressure Hydraulic hoses, motor operation, speed control
Cutter Cuts opening in pipe wall Tooth condition, pilot drill centered, diameter matches
Pilot drill Centers cutter, initial penetration Sharp, proper length (1.5× wall thickness)
Chip collector Captures cutting chips Screen intact, drain valve closed
Isolation valve Seals machine from line Fully open during cutting, test closure before depressurizing

Cutting Parameters

Cutter Speed and Feed Rate: Rotation speed: N = 60-120 RPM for steel pipe Lower speeds for: - Thicker wall (reduce to 30-60 RPM for t > 0.500") - High-strength steel (X70, X80) - Stainless steel or CRA Feed rate: f = 0.002-0.010 inch per revolution (IPR) Cutting time estimate: t_cut = (t_wall / f) / N Where: t_wall = Wall thickness (inches) f = Feed rate (IPR) N = Rotation speed (RPM) Example - 0.375" wall, 80 RPM, 0.005 IPR: t_cut = (0.375 / 0.005) / 80 t_cut = 75 / 80 t_cut = 0.94 minutes ≈ 1 minute Add time for: - Pilot drill penetration: 1-2 minutes - Final break-through: 1 minute - Coupon extraction: 2-5 minutes Total cutting cycle: 5-10 minutes for typical 6" hot tap Larger taps (12-24") with thick walls (0.500-0.750"): Cutting time: 10-30 minutes Total cycle: 20-60 minutes Cutter lubrication: Apply cutting oil or water-soluble coolant continuously during machining: - Reduces heat generation - Extends cutter life - Improves chip evacuation - Reduces friction/torque

Quality Control and Inspection

Post-Tap Inspection: Coupon examination: 1. Verify complete cut (no attached ligaments) 2. Check for burn marks (indicates excessive heat/speed) 3. Measure coupon thickness (verify matches expected) 4. Inspect inner surface (look for corrosion, pitting, coating) 5. Retain coupon (for records, metallurgical analysis if needed) Opening inspection: If accessible (before completion plug installed): 1. Visual inspect cut edge (smooth, perpendicular) 2. Check for burrs or sharp edges (deburr if needed) 3. Verify no damage to pipe interior (deformation, coating) Pressure test: After completion plug installed: - Soap bubble test at atmospheric pressure, or - Hydrotest to 1.5× MAOP for 10 minutes Accept criteria: - No leaks - No visible deformation - Coupon clean cut - Machine operated smoothly (no excessive force or vibration) Documentation: - Coupon photo (both sides) - NDE reports (MT/PT, RT/UT) - Pressure test results - Operating conditions (P, T, flow) during tap - Crew signatures, date/time
Communication is critical: Maintain continuous communication between field crew and control room during tapping. Control room monitors pressures, flow rates, and alarms. Field crew reports cutting progress and any issues. Establish abort criteria (e.g., if pressure drops > 50 psi, stop cutting immediately). Use dedicated radio channel and backup communication.

5. Safety Protocols & Risk Management

Hot tapping is a high-risk operation requiring extensive safety measures.

Image: Hot Tap Work Zone Safety Layout
Plan view showing: hot tap location (center), 25-ft exclusion zone, fire extinguisher locations, wind direction indicator, upwind safe refuge area, equipment staging area, and communication equipment positions.

Hazard Analysis

Hazard Consequence Mitigation
Burn-through during welding Gas/liquid release, fire, explosion Qualified welders, heat input control, UT thickness verification, flow cooling
Fitting weld failure Catastrophic release Design per ASME, NDE 100% of welds, pressure test before tapping
Coupon becomes lodged in machine Cannot close valve, forced release Ensure adequate machine capacity, flow reduction, practice extraction procedure
Valve fails to close Cannot isolate machine for removal Test valve operation before tapping, backup closure method (stopple), emergency procedures
Overpressure of machine Machine burst, injury to crew Pressure test machine, pressure monitoring, relief valve on machine
H₂S exposure (sour service) Acute toxicity, death H₂S monitors, SCBA available, upwind position, two-person rule
Fire/ignition Fire, explosion, personnel injury Hot work permit, fire watch, extinguishers, clear ignition sources, gas detection
Mechanical injury (rotating equipment) Crush, amputation Machine guarding, lockout/tagout, PPE

Personal Protective Equipment (PPE)

Required PPE for Hot Tap Operations: Welding phase: - Fire-resistant clothing (FRC) - Leather welding jacket and gloves - Welding helmet (auto-darkening recommended) - Safety glasses (under helmet) - Steel-toe boots - Hearing protection (welding noise) Hot tapping phase: - FRC (arc-rated for Category 2 minimum) - Face shield (over safety glasses) - Chemical-resistant gloves (nitrile or neoprene) - Steel-toe boots - Hard hat - Hearing protection (machine noise) - H₂S monitor (if sour service) All phases: - High-visibility vest (if vehicle traffic) - Fall protection (if working at height) Specialized PPE (as needed): - SCBA (sour service, emergency use) - Insulated gloves (cold service, cryogenic) - Heat-resistant gloves (hot service > 150°F) - Confined space equipment (if applicable)

Emergency Procedures

Emergency Response Plan: Scenario 1 - Burn-through during welding: 1. Stop welding immediately 2. Evacuate to safe distance (500+ ft upwind) 3. Call 911 if fire or large release 4. Shut remote block valves if accessible (isolate section) 5. Allow leak to vent/burn safely 6. Do not attempt to extinguish gas fire 7. Monitor for dispersion/fire spread 8. After pressure depletes, assess damage and repair Scenario 2 - Valve fails to close after tapping: 1. Attempt to close valve multiple times (cycle open/closed) 2. If cannot close, do not remove machine 3. Keep machine pressurized (equalized with line) 4. Emergency options: a. Install stopple through separate hot tap upstream b. Shutdown line and depressurize (last resort) c. Clamp fitting and machine assembly (if leak develops) 5. Do not depressurize machine until valve holds or line isolated Scenario 3 - Gas release during machine removal: 1. If leak is small (gasket weep), attempt to tighten bolts 2. If leak is large, evacuate immediately 3. Eliminate ignition sources 4. Close upstream/downstream block valves (isolate) 5. Call 911, evacuate public if necessary 6. Monitor with gas detectors 7. After pressure depletes, repair and test Emergency contact information: - Company emergency hotline: [number] - Local fire department: 911 - Nearest hospital: [name, address] - Pipeline control room: [number] - On-call engineer: [number] Emergency equipment on-site: - Fire extinguishers (20-lb ABC, CO₂) - First aid kit - SCBA (2 units minimum for sour service) - Spill kit (absorbent, containment) - Barricade tape, traffic cones

Regulatory Compliance

Regulation Requirement Compliance
DOT 49 CFR 192/195 Pipeline safety, damage prevention, reporting File DOT report if incident occurs, follow operator procedures
OSHA 1910 Hot work permit, confined space, PPE Hot work permit, fire watch, gas detection, PPE per JSA
OSHA 1910.1000 H₂S exposure limits (10 ppm TWA, 15 ppm STEL) Continuous H₂S monitoring, SCBA available, training
EPA SPCC Spill prevention if oil/condensate present Secondary containment, spill kit, SPCC plan
State regulations Varies (permits, notifications, inspections) Check state requirements (Railroad Commission, PUC, DEP)
API 1160/1170 Integrity management, risk assessment Document tap in IMP, assess for HCA proximity

Contractor Qualification

Hot Tap Contractor Selection Criteria: Minimum qualifications: 1. Experience: 50+ hot taps of similar size/pressure 2. Safety record: EMR (Experience Modification Rate) < 1.0 3. Insurance: $5-10M general liability, $1-5M per occurrence 4. Equipment: Owned, maintained, and pressure-tested machines 5. Personnel: Certified welders, trained hot tap operators 6. Procedures: Written, approved by operator, ASME compliant 7. References: 3+ previous clients, similar projects Pre-qualification audit: - Review safety statistics (TRIR, DART rate) - Inspect equipment condition and calibration - Verify welder certifications (AWS, ASME Section IX) - Check machine pressure test records (annual) - Review previous project documentation On-site supervision: - Operator representative present during critical phases - Stop work authority if unsafe conditions observed - Daily toolbox talks (safety, plan for the day) - Audit contractor compliance with procedures Post-project evaluation: - Safety performance (incidents, near-misses) - Quality (welds, coupon inspection, leaks) - Schedule (on-time completion) - Cost (final vs. bid) - Communication (responsiveness, issue resolution) Use evaluation for future contractor selection.
Abort criteria: Establish clear conditions under which tapping operation will be aborted and line shut down. Examples: (1) Pressure drops > 10% during cutting, (2) Excessive vibration or noise from machine, (3) Cannot extract coupon with maximum machine force, (4) Valve will not close after coupon extracted, (5) Gas detection alarm activates near machine, (6) Weather deteriorates (lightning within 10 miles). Brief entire crew on abort criteria before starting.